Panama City: The consortium expanding the Panama Canal is making fresh claims for cost overruns totalling $737 million, officials said on Friday.
Canal administrator Jorge Quijano told reporters that the Panama Canal Authority had received two claims on Tuesday that “will be evaluated” to determine if there is probable cause. But he warned that “at first glance, the issues will be very difficult for the counterparty to justify.”
In the latest setback for the behind-schedule, over-budget upgrade, a union representative said excavation work was on hold after negotiations broke down between the consortium and workers who have been on strike since Tuesday.
About 1,000 workers are on strike, demanding better safety and treatment. Talks between the two sides are due to resume today.
One of the consortium’s latest claims, for $333 million, is related to the weight of the gate for the third set of locks it is building for the canal — at 55,000 tonnes, compared to the 35,000 tonnes initially planned.
But Quijano pointed to a clause in the contract according to which the canal authority would pay up to the value of a gate weighing 49,000 tonnes.
The second claim, for $404 million, is due to delays in the fourth phase of excavation in the Pacific sector.
The consortium, Grupos Unidos por el Canal, says that the delay in excavation work may mean it will not receive water needed to test the gates. Quijano, however, said he has a ‘plan B’ to provide the necessary water for testing.
The canal authority will pay another $120 million in adjustments to the contract and other small claims, Quijano said.
Work began in 2007 to expand the canal with a third set of locks to enable it to handle the modern mega-freighters that global shipping companies prefer.
But the $5.25 billion project has been plagued by delays, strikes and a bitter dispute over $1.6 billion in cost overruns with the consortium carrying out the upgrade, led by Spanish construction firm Sacyr. Initially scheduled for completion in 2014, the project’s due date has been pushed back to early 2016.
Nearby Nicaragua, meanwhile, launched construction on a rival canal. Quijano estimated that the Nicaragua Canal construction would reduce by up to 30 per cent the transit of ships through the Panama Canal, because it is closer to the lucrative market in the United States.
Zelensky calls on Western allies to supply Kyiv with additional air defence systems to protect Kharkiv and other cities
The hospital's specialist medical team has performed five delicate surgeries during the past two days
A helicopter carrying Ebrahim Raisi and his foreign minister crashed on Sunday as it was crossing mountain terrain in heavy fog
The accident shut down the port, though temporary channels have allowed some traffic in and out of Baltimore
Nasser hospital in Khan Younis was attacked by Israeli army for over a week in February, saying Hamas was holding hostages there
The President was speaking at a graduation ceremony at Morehouse College in Atlanta, Georgia
Martin Griffiths says battles near the Rafah and Kerem Shalom crossings in Gaza's south meant the vital routes are effectively blocked
The military launched a crackdown on the Rohingya minority there in 2017 which is now the subject of a United Nations genocide court case