2 units of Barakah plant linked to grid

 

2 units of Barakah plant linked to grid
Since its inception in 2009, Enec has focused on the safe delivery of the UAE Peaceful Nuclear Energy Programme.

Abu Dhabi - Other significant milestones include the energisation of Unit 2 Main Power Transformer (MTR), Excitation Transformer and Unit Auxiliary Power Transformers (UAT).

by

A Staff Reporter

  • Follow us on
  • google-news
  • whatsapp
  • telegram

Published: Thu 4 Jan 2018, 7:54 PM

Last updated: Thu 4 Jan 2018, 10:04 PM

The Emirates Nuclear Energy Corporation (Enec) has successfully connected Units 3 and 4 of the Barakah Nuclear Energy Plant to the UAE electricity transmission grid. The connection is a prerequisite for future testing and allows for the completion of additional auxiliary buildings at both units.
Other significant milestones include the energisation of Unit 2 Main Power Transformer (MTR), Excitation Transformer and Unit Auxiliary Power Transformers (UAT), which allows the initiation of Hot Functional Testing (HFT). "These achievements are a result of our extensive collaboration with our prime contractor and joint venture partner, the Korea Electric Power Corporation (Kepco)," said Mohamed Al Hammadi, CEO of Enec.
"Working together and benefitting from the experience gained when conducting the same work on Unit 1, the teams continue to make significant progress while continuing to implement the highest international standards of safety, security and quality."
"I am proud of the continued adherence to the highest standards of quality and safety displayed by our teams here in Barakah, the largest nuclear construction site in the world. Their commitment and dedication is a key factor in the continued construction of this strategic project that will power the growth of the UAE, and which is now more than 85 per cent complete," added Al Hammadi.
Over the past year, Enec and Kepco have achieved a series of other construction milestones on the units of the Barakah Plant. The reactor containment building liner dome section was installed and concrete pouring for the dome was completed on Unit 3, and the reactor containment liner plate rings, reactor vessel, steam generators and condenser were installed on Unit 4. Meanwhile, testing and commissioning activities are progressing on Units 1 and 2.
Since its inception in 2009, Enec has focused on the safe delivery of the UAE Peaceful Nuclear Energy Programme. The Unit 4 is more than 60 per cent complete, Unit 3 is more than 79 per cent, Unit 2 is more than 90 per cent, and Unit 1 is currently undergoing commissioning and testing, prior to regulatory review and receipt of the operating licence from the Federal Authority for Nuclear Regulation (FANR). All four units will deliver clean, efficient and reliable electricity to the UAE grid, pending regulatory reviews and licensing. When the four reactors are completed, the Barakah Nuclear Energy Plant will save up to 21 million tonnes of carbon emissions each year. 
reporters@khaleejtimes.com
 


More news from