Mattar Al Tayer, Chairman of the Board and Executive Director of the RTA revealed that completion rate in Phase I of the Dubai Water Canal project had hit 40 per cent. Works under Phase I include the construction of a bridge on the Sheikh Zayed Road comprising 8 lanes in each direction.
Click here for map of the Dubai water canal
Al Tayer also reported that completion rate in Phase II, which includes constructing bridges on Al Wasl and Jumeirah Roads, had reached 25 per cent.
“The Contractor of Phase I of the Project started construction works in the Northern Bridge on the Sheikh Zayed Road in the direction of Dubai, nearby the Red Line of Dubai Metro. 50 per cent of excavation works and casting of concrete piles have been completed, and the Northern Bridge is expected to open in the fourth quarter of this year. The construction of the bridge in the direction from Dubai to Abu Dhabi would follow. The company also embarked on constructing service roads in the Business Bay area after shifting the existing utility lines in situ,” explained Al Tayer.
“Phase I of the project comprises constructing a bridge on the Sheikh Zayed Road crossing over the Canal waterway in such a way allowing free navigation around the clock. Impacted roads would be rerouted to ensure a smooth traffic flow between the two shores of the new Canal. The impacted part of Sheikh Zayed Road is about 800 metres long. The project also includes shifting the existing utility lines impacted by the Canal course, in addition to the lighting and water fountains works on the bridge,” stated Al Tayer
Phase II
“Work is progressing according to the plan in Phase II of the project, which includes the construction of bridges on Al Wasl and Jumeirah Roads, with a completion rate of more than 25 per cent. The contractor is currently constructing bridges on Al Wasl Road, where drilling works and casting of concrete piles & columns had been completed. The company also started preparatory works of Phase II of the traffic diversion. In Jumeirah Road, excavation works are underway to protect the utility lines in preparation for constructing the traffic diversion,” RTA Chairman of the Board and Executive Director added.
Al Tayer, extended his sincere thanks to residents and road users in areas impacted by traffic diversion works, for their cooperation with both the RTA and project contractors, which had a significant impact on expediting construction works. “The Dubai Water Canal, a modern, unique, commercial and tourist destination project, would add further glamour to Dubai city and off a new lifestyle experience in the heart of it and at both banks of the Canal,” he said.
Phase III
“Completion rate in Phase III has so far exceeded 15 per cent. Work is currently underway to complete the protection of utility lines and the shifting of sewage lines on both sides of the Canal, besides constructing sewage pumping station and coastal works for the breakwater. Earlier this year, the RTA has reopened the running track of Al Safa Park, which had been impacted by construction works; a step that reflects RTA’s keenness to bring happiness to the people by providing facilities for jogging or walking,” said Al Tayer.
As the RTA is keen to ensure the safety of road users, it has developed a plan for traffic diversions to ensure a smooth traffic flow. The traffic movement has been diverted on both directions of the Sheikh Zayed Road as well as Al Wasl Road.
The RTA has also communicated with all inhabitants of areas impacted by project works and provided them with diversion layouts along with the contractor’s phone numbers. Notices were placed in public places, published in newspapers and social media sites to inform the public about alternative roads.
The deportees were among hundreds of employees, Filipino and foreign, rounded up by an anti-crime government task force in a raid on March 14
world1 hour ago
Certain 'vulnerabilities' could allow attackers to steal data, execute malicious codes, authority says
tech1 hour ago
SAF can reduce lifecycle carbon emissions by up to 80% compared to using conventional jet fuel
aviation1 hour ago
Pant was named in India's T20 World Cup squad after his comeback following a near-fatal car accident in December 2022
cricket2 hours ago
The organisation has established a fact-finding panel to determine the responsibility for the attack
mena2 hours ago
NASA's Solar Dynamics Observatory captured the bright flash of the X-ray flare — it was the strongest since 2005, rated on the scale for these flares as X8.7
world2 hours ago
More construction works are expected at several locations as part of Al Khail Road Improvement Project, which shall be completed in the fourth quarter of 2024
transport2 hours ago
Telecommunication leaders, regulatory authorities, policymakers, industry associations, and leading global technology firms congregated in Dubai at the 5G-Advanced (5G-A) Forum to chart the pathway to the 5G evolution
kt network3 hours ago